S4HANA CS/SD/PS/PP : Block Outbound Delivery Creation upon TECO of Service/Network/Production Order


This is a real time Scenario to block Outbound Delivery Creation  Upon TECO of Service/Network/ Production Order.

Background :

             When we have created a Service Order from Sales Order for Repair Scenario,  We normally take the material into our Stock using Return delivery and get it serviced and send material to customer using Outbound delivery.  Normally TECO will control whether  outbound delivery can be allowed for Material , or it should be scrapped based on the status of Repair.

As per the standard design, Outbound Delivery can be allowed before and After TECO, this is controlled in the system Status


Now we can forbid Delivery Creation for line item,

There are actually two Approaches for this. Let us discuss each in Details


Method 1:

Create a User status Profile and Forbid Creation of Delivery for Outbound Line item


This is Delivery Line with Item Category IRAL, Assign one user Status and make Delivery Creation as Forbid to it


assign this Status to the IRAL item at line item status level

Now try to Create Outbound delivery for this line item and check the results


This is first Approach, Now we discuss in detail on second approach, This is more relavant for Service Order Processing and not useful for other Orders such as Network, Production Order

Method :2

This approach is mainly to Control the Repair Procedure Items, from the Repair Procedure, you can delete the Outbout delivery item

If this item is deleted , after TECO system will automatically propose next Stage. Please ensure to add Item if you need outbound delivery manually in the Order

Comments

Popular posts from this blog

SAP PM/CS / EAM : Refurbishment Process

Refurbishment A refurbishment order is a standard Maintenance Order type. In customizing for order, we first create an order type ( such as PM04) In the configuration we have to create a new order type in OIOA and activate this for Refurbishment process. Process flow: Business process steps 1. Damaged equipment/ spares if can be repaired will be done by the PM order of type PM04 2. Equipment/Spares needs repairing should have the item code if it is serialized item then with the serial number. 3. Item should have the valuation type for repair category too. 4. Create PR through refurbishment order for repair of the item with split valuation type of repair. Proper G/L codes and order for the repair indent should be provided in the indent 5. After approval of the requisition, the requisition and item should be send to the stores/Purchase section for further actions. 6. Stock will get updated after MIGO of the item 7. The activity type cost

TO MAKE INACTIVE CONDITION ACTIVE IN SAP

This blogger contains details on how to set an INACTIVE CONDITION  to ACTIVE while processing Sales Order content: 1.  BUSINESS REQUIREMENT Due to some legal restrictions in Russia, Russia Local Plant cannot hold any stock for the material and hence it is non valuated which means the Standard Price is Zero ( 0 $ ) The stock will be replenished from another company code and we used our Standard Third Party process  in which PR is created which will be converted to PO and when we do GR, the Standard Price of that plant is calculated in the GR. The baseline pricing structure is mapped in such a way that VPRS is calculated from the Material master and on which 15% markup is added as base price. Since the Cost price in VPRS condition is Zero Markup calculated on VPRS will be obviously calculates to Zero and both conditions were set as INACTIVE as per the condition properties 2.  CREATE SALES ORDER we will create a sales order for a material, whose standard Price

S4HANA-Project Systems Operative Indicators in WBS- CJ20N

  Use and Purpose of Operative Indicators in WBS elements When a customer Requests for ATO or ETO process where we create a Project with Integration between SD and PS ( project systems) As a First step we create a Project in CJ20N and under the Project we will Create Multiple WBS elements which has to be set for Operative Indicators This article deals with Operative Indicators in WBS elements. WE Use Operative Indicators to define characteristics of WBS and to specify which tasks WBS can perform during Execution In General, we have three Operative Indicators such as 1. Planning Indicator 2. Account Assignment Indicator 3. Billing Indicator Planning Element: WBS Elements will be set for planning Element,if we we want a plan cost to be enabled For Example, While Creating a Project- Manufacturing an Equipment. We will Create different WBS elements for each Level such as Design, Procurement of components, Production, Assembly and Installation. During Each state some cost is incurred and we