Hello,
In our Item Category definition  VOV7 we have a Field called BILLING FORM 

i would like to give a brief overview of Billing Form and its usage
Definition:-
Unlike our normal Billing ( standard Billing process) we also have a Time and Material Billing which is most widely used in SAP Project systems and Customer service. In this billing process, Customer is billed according to Materials consumed and Labour time booked during the course of project or while performing repair/Service
Billing Form is used to Bill Customer based on Flat-Rate
Usage:-
In order to understand Time and Material Billing , it  is necessary to emphasis on Plan cost and Actual cost
Plan cost is cost which we plan to incur during our execution ( either Project or repair)
Actual Cost is which is actually incurred during out execution.
So here Using Billing Form we will bill customer on Flat Rate Billing which is Planned from Labor hours and Materials consumed
Types: –

We have two types of Billing Forms defined in Standard SAP
1. Fixed Rate
2. Cost
Configuration: –
VOV7 – Item category settings, Maintain Billing form either as 01 ( fixed Rate) or 02 (cost)
Business Scenario:-
1. Customer Requests for Installation of Certain Equipment.
2. You will create a sales order for the customer with Service Product ( such as Installation) and all our standard Determinations will copy as per standard. Item category will be copied in which we have maintained Billing Form as 01 ( fixed Rate).
3. A service Order is created from Sales order to capture the Time and Material Cost
4. For example, you plan 10 hours of Labor hours and few Material Components to perform installation
5. Send Quotation to customer with Plan cost
6. If customer accepts Quotation, Billing Form will create a Debit Memo Request  for Plant cost automatically in Background
Difference Between Fixed Rate and Cost Billing Form:
Case 1: FIXED RATE
When we use Fixed Rate in the Item Category, After accepting quotation, system will create automatically Billing Request from the Plan Cost and after Confirmation of services or components system does not allow to Create a Debit Memo for second time

Case 2: COST 
When we use Fixed Rate in the Item Category, After accepting quotation, system will create automatically Billing Request from the Plan Cost and after Confirmation of services or components system does  allow to Create a Debit Memo for second time

this behavior is standard and it is controlled in Exit  "EXIT_SAPLV46H_001"
Youtube channel link:

https://youtu.be/BoLvKVIHE_8

https://youtu.be/BoLvKVIHE_8


Comments

Post a Comment

Popular posts from this blog

SAP PM/CS / EAM : Refurbishment Process

Refurbishment A refurbishment order is a standard Maintenance Order type. In customizing for order, we first create an order type ( such as PM04) In the configuration we have to create a new order type in OIOA and activate this for Refurbishment process. Process flow: Business process steps 1. Damaged equipment/ spares if can be repaired will be done by the PM order of type PM04 2. Equipment/Spares needs repairing should have the item code if it is serialized item then with the serial number. 3. Item should have the valuation type for repair category too. 4. Create PR through refurbishment order for repair of the item with split valuation type of repair. Proper G/L codes and order for the repair indent should be provided in the indent 5. After approval of the requisition, the requisition and item should be send to the stores/Purchase section for further actions. 6. Stock will get updated after MIGO of the item 7. The activity type cost

TO MAKE INACTIVE CONDITION ACTIVE IN SAP

This blogger contains details on how to set an INACTIVE CONDITION  to ACTIVE while processing Sales Order content: 1.  BUSINESS REQUIREMENT Due to some legal restrictions in Russia, Russia Local Plant cannot hold any stock for the material and hence it is non valuated which means the Standard Price is Zero ( 0 $ ) The stock will be replenished from another company code and we used our Standard Third Party process  in which PR is created which will be converted to PO and when we do GR, the Standard Price of that plant is calculated in the GR. The baseline pricing structure is mapped in such a way that VPRS is calculated from the Material master and on which 15% markup is added as base price. Since the Cost price in VPRS condition is Zero Markup calculated on VPRS will be obviously calculates to Zero and both conditions were set as INACTIVE as per the condition properties 2.  CREATE SALES ORDER we will create a sales order for a material, whose standard Price

S4HANA-Project Systems Operative Indicators in WBS- CJ20N

  Use and Purpose of Operative Indicators in WBS elements When a customer Requests for ATO or ETO process where we create a Project with Integration between SD and PS ( project systems) As a First step we create a Project in CJ20N and under the Project we will Create Multiple WBS elements which has to be set for Operative Indicators This article deals with Operative Indicators in WBS elements. WE Use Operative Indicators to define characteristics of WBS and to specify which tasks WBS can perform during Execution In General, we have three Operative Indicators such as 1. Planning Indicator 2. Account Assignment Indicator 3. Billing Indicator Planning Element: WBS Elements will be set for planning Element,if we we want a plan cost to be enabled For Example, While Creating a Project- Manufacturing an Equipment. We will Create different WBS elements for each Level such as Design, Procurement of components, Production, Assembly and Installation. During Each state some cost is incurred and we