SAP SD/CS/PS Billing Form usage in Item Category VOV7


Hello,
In our Item Category definition  VOV7 we have a Field called BILLING FORM 

i would like to give a brief overview of Billing Form and its usage
Definition:-
Unlike our normal Billing ( standard Billing process) we also have a Time and Material Billing which is most widely used in SAP Project systems and Customer service. In this billing process, Customer is billed according to Materials consumed and Labour time booked during the course of project or while performing repair/Service
Billing Form is used to Bill Customer based on Flat-Rate
Usage:-
In order to understand Time and Material Billing , it  is necessary to emphasis on Plan cost and Actual cost
Plan cost is cost which we plan to incur during our execution ( either Project or repair)
Actual Cost is which is actually incurred during out execution.
So here Using Billing Form we will bill customer on Flat Rate Billing which is Planned from Labor hours and Materials consumed
Types: –

We have two types of Billing Forms defined in Standard SAP
1. Fixed Rate
2. Cost
Configuration: –
VOV7 – Item category settings, Maintain Billing form either as 01 ( fixed Rate) or 02 (cost)
Business Scenario:-
1. Customer Requests for Installation of Certain Equipment.
2. You will create a sales order for the customer with Service Product ( such as Installation) and all our standard Determinations will copy as per standard. Item category will be copied in which we have maintained Billing Form as 01 ( fixed Rate).
3. A service Order is created from Sales order to capture the Time and Material Cost
4. For example, you plan 10 hours of Labor hours and few Material Components to perform installation
5. Send Quotation to customer with Plan cost
6. If customer accepts Quotation, Billing Form will create a Debit Memo Request  for Plant cost automatically in Background
Difference Between Fixed Rate and Cost Billing Form:
Case 1: FIXED RATE
When we use Fixed Rate in the Item Category, After accepting quotation, system will create automatically Billing Request from the Plan Cost and after Confirmation of services or components system does not allow to Create a Debit Memo for second time

Case 2: COST 
When we use Fixed Rate in the Item Category, After accepting quotation, system will create automatically Billing Request from the Plan Cost and after Confirmation of services or components system does  allow to Create a Debit Memo for second time

this behavior is standard and it is controlled in Exit  "EXIT_SAPLV46H_001"
Youtube channel link:

https://youtu.be/BoLvKVIHE_8

https://youtu.be/BoLvKVIHE_8


Comments

Post a Comment

Popular posts from this blog

SAP PM/CS / EAM : Refurbishment Process

Refurbishment A refurbishment order is a standard Maintenance Order type. In customizing for order, we first create an order type ( such as PM04) In the configuration we have to create a new order type in OIOA and activate this for Refurbishment process. Process flow: Business process steps 1. Damaged equipment/ spares if can be repaired will be done by the PM order of type PM04 2. Equipment/Spares needs repairing should have the item code if it is serialized item then with the serial number. 3. Item should have the valuation type for repair category too. 4. Create PR through refurbishment order for repair of the item with split valuation type of repair. Proper G/L codes and order for the repair indent should be provided in the indent 5. After approval of the requisition, the requisition and item should be send to the stores/Purchase section for further actions. 6. Stock will get updated after MIGO of the item 7. The activity type cost ...

SAP SD/CS/PS /PM : System status and User Status a differentiation

In SAP, Master Data and Transaction data is controlled by system status.  But there are certain limitation where system status cannot be used, In such instances a User status can be used. We will see how a system status and User status functions in a particular transaction. Let's understand what is "SYSTEM STATUS" and  "USER STATUS" from system perspective. SYSTEM STATUS:-                                                       A system status is set by the system automatically upon executing a function. It                            Specifies that a particular function was carried out on an Object, be it a                            Transaction ( like Service Order) or a master Data ( serial Nu...

S4HANA/ SD/PP/PS/CS---- Requirements Type and its determination in Sales Order

This Article focuses on Requirement Type and how it is determined in Sales Order. Also  the strategy of Requirement and its Usage Definition of Requirements Type:                Requirement Type Identifies different Requirements like Sales Order, Delivery Requirements,  individual Customer Requirements, Make To Order  or Assembly to Order. Requirements Type uses Planning strategy which has specific strategy for specific Process Requirements Type along with Requirements Class plays a Significant role in determining relevant Functions like, Costing, Settlement, Result analysis, Accounting Indicators,  Special Stock  Indicators, Valuation settings Determining the Requirements Type: To determine  Requirements Type at Sales Order, a sequence of Strategies are defined in Standard Let us check these Strategies 1.  At First, system will check the MATERIAL MASTER--> MRP  3 View-->Strategy...